Completion date of improvement; notice of completion, abandonment or
nonabandonment; contents of notice.
(1) The completion of construction of an improvement shall occur when:
(a) The
improvement is substantially complete;
(b) A completion
notice is posted and recorded as provided by subsections (2) and (3) of this
section; or
(c) The
improvement is abandoned as provided by subsection (5) of this section.
(2) When all
original contractors employed on the construction of an improvement have
substantially performed their contracts, any original contractor, the owner or
mortgagee, or an agent of any of them may post and record a completion notice.
The completion notice shall state in substance the following:
______________________________________________________________________________
Notice hereby is
given that the building, structure or other improvement on the following
described premises, (insert the legal description of the property including the
street address, if known) has been completed.
All persons
claiming a lien upon the same under the Construction Lien Law hereby are
notified to file a claim of lien as required by ORS 87.035.
Dated ______, 2__
____________
Original Contractor,
Owner or Mortgagee
P. O. Address: ______
______________________________________________________________________________
(3) Any notice
provided for in this section shall be posted on the date it bears in some
conspicuous place upon the land or upon the improvement situated thereon.
Within five days from the date of posting the notice, the party posting it or
the agent of the party shall record with the recording officer of the county in
which the property, or some part thereof, is situated, a copy of the notice,
together with an affidavit indorsed thereon or attached thereto, made by the
person posting the notice, stating the date, place and manner of posting the
notice. The recording officer shall indorse upon the notice the date of the
filing thereof and record and index the notice in the statutory lien record as
required by ORS 87.050.
(4) Anyone
claiming a lien created under ORS 87.010 on the premises described in a
completion or abandonment notice for labor or services performed and materials
or equipment used prior to the date of the notice shall perfect the lien
pursuant to ORS 87.035.
(5) Except as
provided in subsection (6) of this section, an improvement is abandoned:
(a) On the 75th
day after work on the construction of the improvement ceases; or
(b) When the
owner or mortgagee of the improvement or an agent of either posts and records
an abandonment notice in writing signed by either the owner or the mortgagee.
(6) When work on
the construction of an improvement ceases, if the owner or mortgagee of the
improvement intends to resume construction and does not want abandonment to
occur, the owner or mortgagee or an agent of either shall post and record a
nonabandonment notice in writing signed by either the owner or mortgagee. The
notice of nonabandonment shall be posted and recorded not later than the 74th
day after work on the construction ceases. The notice of nonabandonment may be
renewed at intervals of 150 days by rerecording the notice.
(7) The notices
of abandonment or nonabandonment described in subsections (5) and (6) of this
section shall state in substance:
(a) That the
improvement is either abandoned or not abandoned.
(b) The legal
description of the property, including the street address if known, on which
the improvement is located.
(c) In the case
of an abandonment notice, that all persons claiming a lien on the improvement
should file a claim of lien pursuant to ORS 87.035.
(d) In the case
of a nonabandonment notice, the reasons for the delay in construction.
(e) The date of
the notice.
(f) The address
of the person who signs the notice. [Amended by 1975 c.466 §11; 1985 c.596 §2;
1987 c.662 §8; 2001 c.577 §6; 2005 c.22 §53]
Plain English Explanation
This Oregon statute addresses Completion date of improvement; notice of completion, abandonment or
. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 87.045
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses Completion date of improvement; notice of completion, abandonment or
. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 87.045. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.