Payments to subcontractors and material suppliers; failure to pay; omission of payment.
(1) An original contractor,
subcontractor or material supplier that performs in accordance with a
construction contract is entitled to payment from the party with whom the
original contractor, subcontractor or material supplier contracts.
(2)(a) If a
subcontractor has performed in accordance with a construction contract, and the
original contractor receives payment from the owner for work performed by the
subcontractor, the original contractor shall pay the subcontractor for that
work no later than seven days after the original contractor receives the
payment. If a material supplier has performed in accordance with a construction
contract, and the original contractor receives payment from the owner for
materials or products provided by the material supplier, the original
contractor shall pay the material supplier for those materials and products no
later than seven days after the original contractor receives the payment. An
original subcontractor that receives payment under this subsection for work
provided to the original subcontractor by another subcontractor, or for
materials or products provided to the original subcontractor, shall pay the
other subcontractor or material supplier for the work, materials or products no
later than seven days after the original subcontractor receives the payment.
(b) Payment is
not required under this subsection unless a subcontractor or material supplier
provides to the original contractor or subcontractor a billing or invoice for
the work performed or materials or products supplied in compliance with the
terms of the contract between the parties. Each subcontractor or material
supplier must provide an appropriate waiver of any lien for labor, equipment,
services, materials or products in accordance with subcontract or purchase
order terms and conditions. The original contractor or subcontractor may
require that such waivers of lien be notarized.
(3) Any failure
to reasonably account for the application or use of payments, as proven in a
legal proceeding authorized under the terms of the construction contract, may
constitute grounds for disciplinary action by the Construction Contractors
Board under ORS 701.098.
(4) An original
contractor that submits a billing or estimate to an owner, or an original
subcontractor that submits a billing or estimate to the original contractor,
may omit from the billing or estimate amounts to be withheld from payment to a
subcontractor or material supplier because of:
(a)
Unsatisfactory work progress;
(b) Defective
construction work, materials or products not remedied;
(c) Disputed
work, materials or products, except that the withheld amount may not exceed 150
percent of the amount in dispute;
(d) Failure to
comply with other material provisions of the construction contract;
(e) A third party
claim being filed or reasonable evidence that a third party claim will be
filed;
(f) Failure of
the subcontractor to make timely payments to subcontractors and material
suppliers for labor, equipment, materials and products;
(g) Damage to an
original contractor, subcontractor or material supplier;
(h) Reasonable
evidence that the subcontract cannot be completed for the unpaid balance of the
subcontract sum; or
(i) Other items
as allowed under the subcontract or purchase order terms and conditions.
(5) An original
contractor or original subcontractor may also omit from a billing or estimate a
reasonable amount for retainage, except that the amount omitted may not exceed
the actual percentage allowed by the construction contract, subcontract or purchase
order. As used in this subsection, retainage has the meaning given that term
in ORS 701.410.
(6) If a progress
or final payment to a subcontractor or material supplier is delayed by more
than seven days after receipt of a progress or final payment by an original
contractor or subcontractor, the original contractor or subcontractor shall pay
its subcontractor or material supplier interest beginning on the eighth day,
except during periods of time during which payment is withheld pursuant to
subsection (4) or (5) of this section, at the rate of one and one-half percent
a month or a fraction of a month on the unpaid balance or at such higher rate
as the parties agree.
(7) In any
action, claim or arbitration brought to collect interest under this section,
the prevailing party shall be awarded costs and reasonable attorney fees. [2003
c.675 §56; 2011 c.553 §3]
Note:
See note under 701.620.
Plain English Explanation
This Oregon statute addresses Payments to subcontractors and material suppliers; failure to pay; omission of payment. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 701.630
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses Payments to subcontractors and material suppliers; failure to pay; omission of payment. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 701.630. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.