Statute Text
Partial payment; retainage; effect; interest; notice of completion; payment by
contractor and owner.
(1) Partial payment is allowed and may be made on contracts for construction
and home improvement. An owner, contractor or subcontractor may withhold as
retainage an amount equal to not more than five percent of the contract price
of the work completed. Partial payment allowed under this subsection is not
acceptance or approval of some of the work or a waiver of defects in the work.
(2) The owner,
contractor or subcontractor shall pay interest at the rate of one percent per
month on the final payment due the contractor or subcontractor. The interest
shall commence 30 days after the contractor or subcontractor has completed and
the owner has accepted the work under the contract for construction for which
the final payment is due. The interest shall run until the date when final
payment is tendered to the contractor or subcontractor. When the contractor or
subcontractor considers the work that the contractor or subcontractor is
contracted to perform to be complete, the contractor or subcontractor shall
notify the party to whom the contractor or subcontractor is responsible for
performing the construction work under the contract. The party shall, within 15
days after receiving the notice, either accept the work or notify the
contractor or subcontractor of work yet to be performed under the contract. If
the party does not accept the work or does not notify the contractor or
subcontractor of work yet to be performed within the time allowed, the interest
required under this subsection shall commence 30 days after the end of the
15-day period.
(3) When a
contractor pays a subcontractor in full, including the amount the contractor
withheld as retainage, the owner with whom the contractor has the contract
shall pay the contractor, out of the amount that the owner withheld from the
contractor as retainage, a sum equal to the amount of retainage that the
contractor paid the subcontractor. The contractor shall notify the owner when
the contractor pays a subcontractor in full under this section and the owner
shall, within 15 days after receiving the notice, pay the contractor the amount
due the contractor under this subsection. Interest on the amount due the
contractor at the rate of one percent per month shall commence 30 days after
the owner receives notice of full payment to the subcontractor. [1975 c.772 §2;
2010 c.77 §8; 2013 c.410 §2; 2019 c.486 §2; 2024 c.2 §3]
Note:
See note under 701.410.
Plain English Explanation
This Oregon statute addresses Partial payment; retainage; effect; interest; notice of completion; payment by
. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 701.420
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses Partial payment; retainage; effect; interest; notice of completion; payment by
. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 701.420. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.