Oregon Revised Statutes Chapter 701 § 701.131 — License required to perfect lien or obtain judicial or administrative remedy;
Oregon Revised Statutes Chapter 701 ·
Oregon Code § 701.131·Enacted ·Last updated March 01, 2026
Statute Text
License required to perfect lien or obtain judicial or administrative remedy;
exception.
(1)
Except as provided in subsection (2) of this section, a contractor may not
perfect a construction lien, file a complaint with the Construction Contractors
Board or commence an arbitration or a claim in a court of this state for
compensation for the performance of any work or for the breach of any contract
for work that is subject to this chapter, unless the contractor had a valid
license issued by the board and properly endorsed for the work performed:
(a) At the time
the contractor bid or entered into the contract for performance of the work;
and
(b) Continuously
while performing the work for which compensation is sought.
(2) The board,
arbitrator or court may not apply the provisions of subsection (1) of this
section to a contractor if the board, arbitrator or court determines that:
(a) The
contractor either did not have a valid license with a proper endorsement at any
time required under subsection (1) of this section, or had an initial issuance
of a valid license, and:
(A) The
contractor was not aware of the requirement that the contractor be licensed or
properly endorsed for the work performed, and the contractor submitted a
completed application for a license within a number of days established by the
board, but not more than 90 days, of the date the contractor became aware of
the requirement;
(B) At the time
the contractor perfected a construction lien or commenced any claim subject to
the provisions of subsection (1) of this section, the contractor was licensed
by the board and properly endorsed for the work performed; and
(C) Enforcement
of the provisions of subsection (1) of this section would result in substantial
injustice to the contractor;
(b) The
contractor was licensed by the board for some but not all of the times required
under subsection (1) of this section and had a lapse in the license and:
(A) The
contractor was not aware of the lapse in the license for more than a number of
days established by the board, but not to exceed 90 days, before submitting a
completed application for license renewal with the board;
(B) Except for
perfection of a construction lien and a court action to foreclose the lien, at
the time the contractor commenced any claim subject to the provisions of
subsection (1) of this section the contractors license was renewed under ORS
Plain English Explanation
This Oregon statute addresses License required to perfect lien or obtain judicial or administrative remedy;
. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 701.131
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses License required to perfect lien or obtain judicial or administrative remedy;
. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 701.131. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.