(1) Upon the failure of any parties having contracts
with the state for the construction of irrigation works, to begin the same
within the time specified by the contract, or to complete the same within the
time or in accordance with the specifications of the contract with the state,
to the satisfaction of the Water Resources Commission, the commission shall
give the parties written notice of such failure. If after a period of 60 days
from the sending of such notice they have failed to proceed with the work or to
conform to the specifications of their contract with the state, or secure an
extension of time, their contract and all works constructed thereunder shall be
at once forfeited to the state.
(2) In case of
any forfeiture, cancellation, or relinquishment of any contract to the state,
the commission shall so declare and give notice once each week, for four weeks,
in some newspaper of general circulation in the county in which the work is
situated, and in one newspaper at the state capital in like manner and for a
like period, of the forfeiture, cancellation, or relinquishment of the
contract, and that upon a fixed day proposals will be received at the office of
the commission for purchase of the incompleted works and for completion of the
irrigation works in accordance with plans, specifications and other conditions
prescribed by the commission, the time for receiving bids to be at least 60
days subsequent to the issuing of the last notice of forfeiture. The money
received by the commission from sale of the partially completed works under the
provisions of this section shall first be applied to the expenses incurred by
the state in their forfeiture and disposal, and the surplus, if any exists, shall
be paid to the original contractors with the state.
Plain English Explanation
This Oregon statute addresses Nonperformance by contractor; forfeiture; notice of forfeiture; sale of
. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 555.100
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses Nonperformance by contractor; forfeiture; notice of forfeiture; sale of
. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 555.100. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.