Oregon Revised Statutes Chapter 543 § 543.088 — Payment of costs or fee for reauthorization or relicensing of project
Oregon Revised Statutes Chapter 543 ·
Oregon Code § 543.088·Enacted ·Last updated March 01, 2026
Statute Text
Payment of costs or fee for reauthorization or relicensing of project.
(1) Notwithstanding ORS 543A.405
and 543A.410, during each year of the interim period established in subsection
(2) of this section, any licensee or water right certificant seeking
reauthorization of a state water right to operate a federally licensed hydroelectric
project shall pay the greater of:
(a) The actual
cost of the Hydroelectric Application Review Teams reauthorization activities
for the year in question as established pursuant to ORS 543A.405 and 543A.410;
or
(b) 12.5 cents
per theoretical horsepower as specified in the water right for each project
under consideration for reauthorization. This amount shall be calculated in
1998 dollars.
(2) For any
project, the interim period referred to in subsection (1) of this section shall
begin on the January 1 immediately following submission to the Water Resources
Department of a proposed final order for reauthorization of the project under
ORS 543A.115 (2). For any project, the interim period referred to in subsection
(1) of this section shall end on December 31 of the year the department issues
a final order on reauthorization of the project pursuant to ORS 543A.130.
(3)
Notwithstanding ORS 543.090, during each year of the interim period established
in subsection (4) of this section, any power claimant or uncertificated
claimant seeking to relicense a federally licensed hydroelectric project shall
pay the greater of:
(a) The actual
cost of the teams relicensing activities for the year in question as
established pursuant to ORS 543.090; or
(b) 12.5 cents
per theoretical horsepower as specified in the water right for each project
under consideration for relicensing. This amount shall be calculated in 1998
dollars.
(4) For any
project, the interim period referred to in subsection (3) of this section shall
begin on the January 1 immediately following issuance of an annual license for
the project by the Federal Energy Regulatory Commission. For any project, the
interim period referred to in subsection (3) of this section shall end on
December 31 of the year the Federal Energy Regulatory Commission issues a new
license for the project.
(5) The Water
Resources Department shall reimburse a participating agency for costs incurred
in the agencys review of a project during the year for which the fees are
collected. Such costs shall not include expenses of other state agencies for
which a fee is otherwise collected under state law. Any fees collected under
subsection (1) or (3) of this section in excess of the teams actual cost of
evaluation of the project for the year shall be distributed according to ORS
536.015.
(6) No fee shall
be charged under this section unless the project is a federally licensed
project.
(7) No fee shall
be charged pursuant to subsection (1) of this section unless the Hydroelectric
Application Review Team proposes to reauthorize the water right for the project
in the proposed final order submitted to the Water Resources Department under ORS
543A.115 (2).
(8) Water right
certificants and licensees with water rights or licenses that expire more than
five years after the original federal license for the project expires shall not
begin paying fees assessed under this section until after the expiration date of
the original state hydroelectric license or water right. [1999 c.873 §9]
Plain English Explanation
This Oregon statute addresses Payment of costs or fee for reauthorization or relicensing of project. AI-powered analysis coming soon.
Key Points
01Part of Oregon statutory law
02Referenced as Oregon Code § 543.088
03Subject to legislative amendments
04Consult a licensed attorney for application to specific cases
Frequently Asked Questions
This section of Oregon law addresses Payment of costs or fee for reauthorization or relicensing of project. Read the full statute text above for details.
This page reflects the current text as of our last update. Always verify with the official Oregon legislature website for the most current version.
The formal citation is Oregon Code § 543.088. Use this format in legal documents and court filings.
Browse related sections using the links below, or search all Oregon statutes on FlawFinder.