NOT FOR PUBLICATION FILED
UNITED STATES COURT OF APPEALS JUN 6 2025
MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
FOR THE NINTH CIRCUIT
DRUM LODGE, LLC, No. 24-2833
D.C. No.
Petitioner - Appellant, 2:24-cv-00219-WBS-JDP
v.
MEMORANDUM*
MARTEL CONSTRUCTION, INC.,
Respondent - Appellee.
Appeal from the United States District Court
for the Eastern District of California
William B. Shubb, District Judge, Presiding
Argued and Submitted April 1, 2025
Pasadena, California
Before: M. SMITH and VANDYKE, Circuit Judges, and MAGNUS-STINSON,
District Judge.**
Petitioner Drum Lodge, LLC (Drum Lodge) appeals from a final judgment of
the district court dismissing Drum Lodge’s petition to vacate an arbitration award in
favor of Martel Construction, Inc. (Martel) and the accompanying award of
*
This disposition is not appropriate for publication and is not precedent
except as provided by Ninth Circuit Rule 36-3.
**
The Honorable Jane Magnus-Stinson, United States District Judge for
the Southern District of Indiana, sitting by designation.
attorneys’ fees. We have jurisdiction under 28 U.S.C. § 1291, and we affirm.
Because the parties are familiar with the facts and background of this case, we
provide only the information necessary to give context to our ruling. Martel and
Drum Lodge entered into arbitration before a three-member tribunal to resolve
disputes related to a construction project. The tribunal ultimately decided in favor
of Martel, concluding that Drum Lodge had breached the parties’ contract and was
liable for damages. The tribunal further ordered Drum Lodge to pay Martel’s
attorneys’ fees pursuant to Rule 48(d)(ii) of the Construction Rules of the American
Arbitration Association, which was incorporated into the parties’ contract. Drum
Lodge filed a petition to vacate the arbitration award and award of attorneys’ fees,
but the district court dismissed the petition. Drum Lodge raises two challenges to
this dismissal, both of which fail.
1. Drum Lodge first argues that the award of attorneys’ fees should be
vacated pursuant to 9 U.S.C. § 10(a)(4) because the tribunal exceeded its authority
in awarding attorneys’ fees to Martel. We do not agree. Section 10(a)(4) presents
“a high standard for vacatur.” HayDay Farms, Inc. v. FeeDx Holdings, Inc., 55 F.4th
1232, 1240 (9th Cir. 2022) (quoting Lagstein v. Certain Underwriters at Lloyd’s,
London, 607 F.3d 634, 641 (9th Cir. 2010)). To satisfy this standard, “it is not
enough to show that the arbitrator committed an error—or even a serious error.” Id.
(alterations omitted) (quoting Lagstein, 607 F.3d at 641). Instead, “[a]rbitrators
2 24-2833
exceed their powers . . . not when they merely interpret or apply the governing law
incorrectly, but when the award is completely irrational, or exhibits a manifest
disregard of law.” U.S. Life Ins. Co. v. Superior Nat’l Ins. Co., 591 F.3d 1167, 1177
(9th Cir. 2010) (alteration in original) (quoting Schoenduve Corp. v. Lucent Techs.,
Inc., 442 F.3d 727, 731 (9th Cir. 2006)).
That standard is not met here for two reasons. First, the tribunal reasonably
interpreted Construction Rule 48(d)(ii) to authorize the award of attorneys’ fees here
in light of the facts that (1) Martel requested prevailing party fees and (2) Drum
Lodge requested attorneys’ fees, at a minimum, pursuant to the contract’s
indemnification provision. Contrary to Drum Lodge’s focus on whether it asked for
prevailing-party attorneys’ fees, Construction Rule 48(d)(ii) can be reasonably
interpreted to apply when all parties request some form of attorneys’ fees—which
indisputably occurred here. There is thus no basis to disturb the arbitrator’s decision.
See HayDay Farms, 55 F.4th at 1241 (“[A]n arbitrator does not exceed its authority
if the decision is a plausible interpretation of the arbitration contract. Accordingly,
the court must defer to the arbitrator’s decision as long as the arbitrator even
arguably construed or applied the contract.” (citation omitted) (quoting U.S. Life Ins.
Co., 591 F.3d at 1177)).
Second, even if we were to accept Drum Lodge’s argument that a request for
fees under the contract’s indemnification provision is insufficient to trigger the
3 24-2833
application of Construction Rule 48(d)(ii), Drum Lodge’s challenge still fails. The
tribunal made a finding that, when questioned, Drum Lodge orally represented that
it was seeking attorneys’ fees and “did not condition or limit its affirmative answer
to success on its indemnity counterclaim.” Our review of arbitration decisions is
limited, and “[w]hether or not the panel’s findings are supported by the evidence in
the record is beyond the scope of our review.” Bosack v. Soward, 586 F.3d 1096,
1105 (9th Cir. 2009). We must accept the tribunal’s finding on this point, see
HayDay Farms, 55 F.4th at 1241, and, in light of that finding, an award of attorneys’
fees pursuant to Construction Rule 48(d)(ii) was permissible.
2. Drum Lodge next argues that the arbitration award must be vacated on
grounds of evident partiality pursuant to 9 U.S.C. § 10(a)(2) because the award was
infected by a conversation that occurred between Martel’s counsel and the tribunal
members about the possibility of the members serving on future tribunals in
Montana. Again, we disagree.
To begin, Drum Lodge waived this issue. The waiver doctrine precludes a
party from seeking vacatur of an arbitration award on the grounds of evident
partiality “where [the] party . . . has constructive knowledge of a potential conflict
but fails to timely object.” Fid. Fed. Bank, FSB v. Durga Ma Corp., 386 F.3d 1306,
1313 (9th Cir. 2004); see also Monster Energy Co. v. City Beverages, LLC, 940 F.3d
1130, 1134 (9th Cir. 2019). Here, as shown in the relevant declarations, Drum Lodge
4 24-2833
had actual knowledge of “the key fact that triggered the specter of partiality,”
Monster Energy, 940 F.3d at 1135, but concededly failed to raise any partiality
argument before the arbitrators. The issue is thus waived.
Even if we were to reach the issue, we would reject Drum Lodge’s arguments.
In the absence of actual bias, the possible conflict at issue must be undisclosed to
give rise to an evident-partiality claim. See Lagstein, 607 F.3d at 645–46. But, here,
Drum Lodge’s counsel was in the same room when the allegedly improper
conversation occurred. It is hard to see how the bald assertion by Drum Lodge’s
counsel that he “was under the impression that neither [Martel’s counsel] nor the
arbitrators were aware of [his] presence” during the conversation could be sufficient
to show that the conversation was undisclosed. Moreover, the conversation at issue
here was simply too general and abstract to give rise to “[a] reasonable impression
of bias.” Id. at 646 (alteration in original) (quoting Woods v. Saturn Distrib. Corp.,
78 F.3d 424, 427 (9th Cir. 1996)); cf. Valrose Maui, Inc. v. Maclyn Morris, Inc., 105
F. Supp. 2d 1118, 1124 (D. Haw. 2000) (finding evident partiality when an arbitrator
failed to disclose that he had agreed to mediate in a separate malpractice case on
behalf of one party’s attorney).
AFFIRMED.
5 24-2833
Plain English Summary
NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 6 2025 MOLLY C.
Key Points
01NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 6 2025 MOLLY C.
03Shubb, District Judge, Presiding Argued and Submitted April 1, 2025 Pasadena, California Before: M.
04SMITH and VANDYKE, Circuit Judges, and MAGNUS-STINSON, District Judge.** Petitioner Drum Lodge, LLC (Drum Lodge) appeals from a final judgment of the district court dismissing Drum Lodge’s petition to vacate an arbitration award in favor of
Frequently Asked Questions
NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 6 2025 MOLLY C.
FlawCheck shows no negative treatment for Drum Lodge, LLC v. Martel Construction, Inc. in the current circuit citation data.
This case was decided on June 6, 2025.
Use the citation No. 10599891 and verify it against the official reporter before filing.